How long does it take to install a new kitchen?
How long does it take to install a new kitchen?
A typical kitchen renovation in Ottawa takes 2-4 weeks for installation once materials arrive, but the complete project timeline from design to completion usually spans 8-12 weeks. The actual construction phase depends heavily on the scope of work, size of your kitchen, and whether you're doing a simple refresh or a complete gut renovation.
For a standard kitchen renovation (new cabinets, countertops, appliances, flooring, and paint), expect about 10-15 working days of active construction. This includes 2-3 days for demolition, 3-4 days for electrical and plumbing rough-in work, 2-3 days for drywall and painting, 2-3 days for cabinet installation, 1 day for countertop templating and installation, and 1-2 days for final connections and trim work.
More extensive renovations take longer. If you're moving walls, adding an island, or dealing with structural changes, add another 1-2 weeks. Older Ottawa homes (pre-1960s) often present surprises like outdated electrical panels, cast iron plumbing, or structural issues that can extend timelines. We frequently encounter knob-and-tube wiring in Centretown and Glebe homes, which requires updating before kitchen work can proceed safely.
The biggest timeline factors are permitting and material delivery. In Ottawa, electrical permits through the Electrical Safety Authority (ESA) typically take 1-2 weeks to process, and if you're doing structural work, building permits from the City of Ottawa can take 2-4 weeks. Material delays, especially for custom cabinets or specialty appliances, often add 4-8 weeks to the front end of the project.
Seasonal considerations matter in Ottawa. Spring and summer are peak renovation seasons, so book early if you want work completed during these months. Winter installations can actually move faster due to contractor availability, but material deliveries may face weather delays.
Professional coordination is crucial for keeping timelines on track. Licensed electricians must handle all wiring changes, and plumbers are required for any gas line work to ranges or for moving water lines. The sequence matters - rough trades first, then drywall, then finishes. Poor coordination between trades is the number one cause of kitchen renovation delays.
For a realistic timeline on your specific kitchen project, we offer free consultations where we can assess your space, discuss your goals, and provide a detailed schedule that accounts for permits, materials, and the unique characteristics of your Ottawa home.
Construction Brain — Built by a licensed contractor with 20+ years in the field. Powered by AI with strict guidelines and real building knowledge.
Ready to Start Your Project?
Get a free, no-obligation estimate for your Ottawa renovation. Our team at JRC is ready to help bring your vision to life.