# Home Renovation Timeline Guide: What to Expect in Ottawa
*Last updated: December 2025 | Read time: 8 min*
Understanding realistic timelines helps you plan your renovation, arrange temporary living situations if needed, and set proper expectations. This guide breaks down typical durations for common Ottawa renovation projects.
**Quick answer:** A bathroom takes 2-4 weeks. A kitchen takes 4-8 weeks. A full basement takes 6-12 weeks. Add 2-4 weeks for design/planning and 2-6 weeks for permits.
## Table of Contents
1. [Project Timeline Overview](#overview)
2. [Pre-Construction Phase](#pre-construction)
3. [Bathroom Timelines](#bathroom)
4. [Kitchen Timelines](#kitchen)
5. [Basement Timelines](#basement)
6. [What Causes Delays](#delays)
7. [How to Stay on Schedule](#on-schedule)
---
## Project Timeline Overview {#overview}
### Quick Reference
| Project | Planning | Permits | Construction |
|---------|----------|---------|--------------|
| Powder room | 1-2 weeks | None usually | 1-2 weeks |
| Full bathroom | 2-4 weeks | 1-2 weeks | 2-4 weeks |
| Kitchen refresh | 1-2 weeks | None | 1-2 weeks |
| Full kitchen | 4-8 weeks | 2-3 weeks | 4-8 weeks |
| Basement (basic) | 2-4 weeks | 2-4 weeks | 4-8 weeks |
| Basement (with bathroom) | 4-6 weeks | 3-5 weeks | 6-12 weeks |
| Secondary dwelling unit | 6-10 weeks | 6-12 weeks | 12-20 weeks |
### Total Project Duration
From first call to final walk-through:
| Project Type | Total Duration |
|--------------|---------------|
| Cosmetic updates | 2-4 weeks |
| Single bathroom | 6-10 weeks |
| Kitchen renovation | 10-16 weeks |
| Basement finishing | 12-20 weeks |
| Major whole-home | 6-12 months |
---
## Pre-Construction Phase {#pre-construction}
### Step 1: Initial Consultation (1-2 weeks)
- Meet with contractor(s)
- Discuss scope and budget
- Get quotes
- Compare and select contractor
### Step 2: Design & Planning (2-6 weeks)
| Task | Duration |
|------|----------|
| Detailed design/drawings | 1-3 weeks |
| Material selections | 1-2 weeks |
| Final quote approval | 1 week |
| Scheduling | Varies |
**What takes time:**
- Custom cabinet design
- Picking tile/fixtures
- Getting accurate measurements
- Revisions to plans
### Step 3: Permits (if required) (2-6 weeks)
City of Ottawa typical timelines:
- Simple residential: 10-15 business days
- Complex residential: 15-25 business days
- Secondary dwelling units: 30-45 business days
**Don't start work until permits are in hand**
### Step 4: Material Ordering (2-8 weeks)
| Item | Lead Time |
|------|-----------|
| Stock cabinets | 1-2 weeks |
| Semi-custom cabinets | 4-8 weeks |
| Custom cabinets | 6-12 weeks |
| Special order tile | 2-4 weeks |
| Custom countertops | 2-3 weeks after template |
| Windows/doors | 4-8 weeks |
| Specialty fixtures | 2-6 weeks |
**Pro tip:** Order long-lead items early, even before final permit
---
## Bathroom Timelines {#bathroom}
### Powder Room (Half Bath)
Simple update: **3-5 days**
- New vanity, toilet, mirror, paint
- No tile work
Full renovation: **1-2 weeks**
- New flooring
- New vanity and toilet
- Fresh paint
- Minimal tile
### Full Bathroom (3-piece)
| Phase | Duration |
|-------|----------|
| Demo | 1-2 days |
| Rough plumbing/electrical | 1-2 days |
| Inspection | 1-3 days wait |
| Drywall | 2-3 days |
| Tile installation | 3-5 days |
| Fixture installation | 1-2 days |
| Finishing touches | 1-2 days |
| **Total** | **2-4 weeks** |
### Master Bathroom (4-piece, complex)
| Phase | Duration |
|-------|----------|
| Demo | 2-3 days |
| Rough-in work | 2-4 days |
| Inspections | 2-5 days |
| Drywall/cement board | 2-3 days |
| Tile (floor + shower) | 5-8 days |
| Countertop install | 1-2 days |
| Fixtures | 2-3 days |
| Finishing | 2-3 days |
| **Total** | **4-6 weeks** |
---
## Kitchen Timelines {#kitchen}
### Kitchen Refresh
Cosmetic update: **1-2 weeks**
- Cabinet painting/refacing
- New hardware
- Backsplash
- No layout changes
### Moderate Kitchen Renovation
| Phase | Duration |
|-------|----------|
| Demo (keeping layout) | 1-2 days |
| Electrical updates | 1-2 days |
| Cabinet installation | 2-4 days |
| Counter template | 1 day |
| Counter fabrication | 1-2 weeks |
| Counter installation | 1 day |
| Backsplash | 2-3 days |
| Appliances + fixtures | 1-2 days |
| Finishing | 1-2 days |
| **Total** | **4-6 weeks** |
### Full Kitchen Gut Renovation
| Phase | Duration |
|-------|----------|
| Complete demo | 2-4 days |
| Electrical rough-in | 2-3 days |
| Plumbing (if moving) | 1-2 days |
| Inspections | 3-5 days |
| Drywall repair | 2-3 days |
| Cabinet installation | 3-5 days |
| Flooring | 2-4 days |
| Counter installation | 1-2 days |
| Backsplash | 2-4 days |
| Appliances | 1 day |
| Electrical finishing | 1-2 days |
| Paint and finish | 2-3 days |
| **Total** | **6-10 weeks** |
**Why so long?** Counter fabrication creates a gap - template after cabinets, 1-2 week fabrication, then install.
---
## Basement Timelines {#basement}
### Basic Basement Finish (no bathroom)
| Phase | Duration |
|-------|----------|
| Framing | 3-5 days |
| Electrical rough-in | 2-3 days |
| HVAC (if needed) | 1-2 days |
| Insulation | 1-2 days |
| Drywall | 3-5 days |
| Taping/mudding | 3-4 days (with drying) |
| Flooring | 2-4 days |
| Trim and doors | 2-3 days |
| Paint | 2-3 days |
| Electrical finishing | 1-2 days |
| **Total** | **4-6 weeks** |
### Basement with Bathroom
Add to above timeline:
| Phase | Duration |
|-------|----------|
| Concrete cutting | 1 day |
| Rough plumbing | 2-3 days |
| Plumbing inspection | 1-3 days wait |
| Concrete repair | 1 day + cure time |
| Bathroom tile | 3-5 days |
| Fixture install | 1-2 days |
| **Additional time** | **2-4 weeks** |
**Total with bathroom: 6-10 weeks**
### Full Secondary Dwelling Unit
| Phase | Duration |
|-------|----------|
| Permits | 6-12 weeks |
| Framing + egress | 1-2 weeks |
| Rough-in (all trades) | 2-3 weeks |
| Inspections | 1-2 weeks |
| Drywall | 1-2 weeks |
| Finishing work | 3-4 weeks |
| Final inspections | 1-2 weeks |
| **Total** | **12-20 weeks** |
---
## What Causes Delays {#delays}
### Common Delay Factors
| Issue | Typical Delay |
|-------|--------------|
| Permit delays | 1-4 weeks |
| Material backorders | 1-6 weeks |
| Hidden damage (rot, mold) | 1-2 weeks |
| Inspection failures | 3-7 days |
| Client decision delays | Varies |
| Weather (exterior work) | Days to weeks |
| Subcontractor scheduling | 1-2 weeks |
### Unexpected Discoveries
Common surprises behind walls:
- Outdated electrical (knob and tube)
- Old plumbing needing replacement
- Asbestos or lead paint
- Water damage or mold
- Structural issues
- Incorrect rough-in locations
**Always budget extra time and money for surprises**
### Seasonal Considerations (Ottawa)
| Season | Notes |
|--------|-------|
| Spring | Popular time, contractors busy |
| Summer | Vacation schedules, trades busy |
| Fall | Good time, less competition |
| Winter | Interior work fine, exterior limited |
---
## How to Stay on Schedule {#on-schedule}
### Before Construction
1. **Make decisions early** - Indecision delays everything
2. **Order materials ahead** - Long-lead items especially
3. **Finalize scope** - Changes during construction cause delays
4. **Prepare your home** - Clear work areas in advance
### During Construction
1. **Be available** - Contractors need decisions quickly
2. **Trust the process** - Some stages take time
3. **Communicate concerns** - Don't let issues fester
4. **Expect some disruption** - It's a construction zone
### What You Can Control
- Quick decision-making
- Prompt payments (keeps work flowing)
- Realistic expectations
- Flexibility when surprises arise
- Clear communication
### What You Can't Control
- Permit processing times
- Inspection scheduling
- Material supply chain
- Weather (for some work)
- Hidden conditions
---
## Planning Tips
### Living Arrangements
**Bathroom renovation:**
- Usually can stay (use another bathroom)
- One bathroom home: Plan alternative (gym, neighbour)
**Kitchen renovation:**
- Set up temporary kitchen area
- Microwave, toaster oven, coffee maker
- BBQ for cooking
- Consider paper plates
**Major renovation:**
- May need to move out
- Factor into budget
- Plan for pets too
### Communication Preferences
Establish upfront:
- How often for updates (daily, weekly)
- Preferred method (text, email, phone)
- Who makes decisions
- How to handle after-hours questions
---
*Ready to start planning your renovation timeline? [Contact us](/contact) for a realistic project schedule.*
The Bottom Line
Contact us to discuss your renovation project. We're happy to answer any questions you have.
Ready to Start Your Basement Project?
Get a free, instant estimate for your Ottawa basement renovation. No obligation - just accurate pricing in 60 seconds.
Get Free Estimate