# Kitchen Renovation Timeline: What to Expect Week by Week

# Kitchen Renovation Timeline: What to Expect Week by Week

Kitchen renovations are notorious for taking longer than expected. Here's what actually happens during a kitchen remodel—and realistic timelines for each phase.

## Before Construction: The Hidden Timeline

### Design Phase (4-12 weeks)

**What's happening:**

- Initial consultations

- Measurements and existing conditions

- Design development and revisions

- Material selections

- Final design approval

**Don't rush this.** Design changes during construction cost 10x what they cost during planning.

### Ordering Phase (4-16 weeks)

**What's happening:**

- Cabinet orders (custom: 8-16 weeks; stock: 2-4 weeks)

- Countertop templates (after cabinets, before install)

- Appliance orders (can be quick or months depending on model)

- Flooring and tile orders

- Fixture orders

**Critical path item:** Cabinets. Everything waits for cabinets.

### Permit Phase (2-4 weeks in Ottawa)

**What's happening:**

- Application preparation

- City review

- Approval or revision requests

**Note:** Some kitchen work needs permits (electrical, plumbing, structural); cosmetic doesn't.

## Construction Timeline: Week by Week

### Week 1: Demolition and Discovery

**Day 1-2: Preparation**

- Clear kitchen completely

- Set up dust barriers

- Protect adjacent areas

- Establish temporary kitchen setup

**Day 3-5: Demolition**

- Remove cabinets, counters, backsplash

- Remove flooring if replacing

- Disconnect appliances and plumbing

- Remove drywall where needed

**The discovery phase:**

This is when surprises emerge—hidden rot, outdated wiring, plumbing issues. Budget and timeline need flexibility here.

**Milestone:** Empty room, ready for rough-in

### Week 2: Rough-In Work

**Electrical rough-in:**

- Move/add outlets

- Add circuits for new appliances

- Lighting rough-in

- Under-cabinet lighting prep

**Plumbing rough-in:**

- Move supply lines if needed

- Adjust drain locations

- Gas line work if applicable

- Dishwasher and fridge connections

**Structural work:**

- Any wall modifications

- Header installation if removing walls

- Soffit modifications

**HVAC adjustments:**

- Duct relocations

- Range hood venting

**Milestone:** All rough-in complete, ready for inspection

### Week 3: Inspection and Drywall

**Day 1-2: Inspections**

- Electrical inspection

- Plumbing inspection

- Structural inspection (if applicable)

**Day 3-5: Drywall and Patching**

- New drywall where needed

- Patching and repair

- Tape and first coat

**Milestone:** Passed inspections, walls closed up

### Week 4: Drywall Finishing and Painting

**Day 1-3: Drywall finishing**

- Second and third coats

- Sanding

- Texture matching (if applicable)

**Day 4-5: Painting**

- Prime new drywall

- Ceiling paint

- Wall paint (first coat minimum)

**Why paint now:** Easier before cabinets are in. Touch-up after, but base coats now.

**Milestone:** Walls and ceiling finished

### Week 5: Flooring

**Depends on material:**

- Tile: 3-5 days (including grout cure time)

- Hardwood: 3-4 days

- LVP: 1-2 days

**Timing options:**

- Some prefer flooring before cabinets (continuous floor)

- Some prefer after cabinets (less waste, protects floor)

- Both approaches work; discuss with contractor

**Milestone:** Flooring complete

### Week 6: Cabinet Installation

**Day 1-2: Base cabinets**

- Level and secure to walls

- Install corner and standard bases

- Ensure level and plumb

**Day 3-4: Wall cabinets**

- Install upper cabinets

- Align with base cabinets

- Install crown molding if applicable

**Day 5: Adjustments and trim**

- Door adjustments

- Hardware installation

- Filler pieces and trim

**Milestone:** Cabinets installed, ready for countertop template

### Week 7: Countertop Fabrication

**Day 1: Template**

- Fabricator creates precise template

- Final sink/cooktop cutout locations

- Edge details confirmed

**Day 2-5: Fabrication**

- Countertops cut and polished

- Cutouts made

- Edges finished

**This week feels slow** but fabrication takes time for precision.

**Milestone:** Countertops fabricated, ready for install

### Week 8: Countertop Install and Plumbing

**Day 1-2: Countertop installation**

- Counters set in place

- Seams joined

- Sink cut-outs finalized

**Day 2-3: Sink and faucet**

- Sink installation

- Faucet installation

- Garbage disposal if applicable

- Connections to plumbing

**Day 4-5: Appliance plumbing**

- Dishwasher installation

- Ice maker connection

- Gas range connection

**Milestone:** Working sink, countertops installed

### Week 9: Electrical Finish and Appliances

**Day 1-2: Electrical finish**

- Install outlets and covers

- Install switches

- Under-cabinet lighting

- Pendant/fixture installation

**Day 3-4: Appliances**

- Range/cooktop installation

- Refrigerator placement

- Microwave/hood installation

- Dishwasher final connection

**Day 5: Testing**

- Test all appliances

- Check all connections

- Verify everything works

**Milestone:** Functional kitchen

### Week 10: Backsplash and Details

**Day 1-3: Backsplash installation**

- Tile setting

- Grout

- Caulk at countertop

**Day 4-5: Finishing touches**

- Paint touch-up

- Cabinet adjustment

- Hardware tightening

- Caulk and sealant

- Trim pieces

**Milestone:** Backsplash complete

### Week 11: Punch List and Completion

**Day 1-3: Punch list**

- Final inspection walk-through

- Note any issues

- Address corrections

**Day 4-5: Final details**

- Complete punch list items

- Deep cleaning

- Final inspection

- Project handoff

**Milestone:** Project complete

## Total Timeline Summary

| Phase | Duration |

|-------|----------|

| Design | 4-12 weeks |

| Ordering | 4-16 weeks |

| Permits | 2-4 weeks |

| Construction | 8-11 weeks |

| **Total** | **18-43 weeks** |

## What Affects Timeline

### Makes It Longer:

- Custom cabinets vs. stock

- Structural changes

- Moving plumbing significantly

- Permit delays

- Material delays

- Discovery of hidden issues

- Change orders

### Can Shorten It:

- Stock cabinets in standard sizes

- No structural changes

- Plumbing staying in place

- Materials ordered early

- Clear decisions from start

- Experienced contractor

## Living Through It

### Temporary Kitchen Setup

**Essential:**

- Microwave

- Electric kettle

- Toaster oven

- Mini fridge

- Basic dishes and utensils

**Location:** Dining room, basement, or garage

### Realistic Expectations

- You'll eat out more than planned

- Dust gets everywhere despite barriers

- There will be at least one unexpected issue

- Some days will feel like nothing's happening

- The last 10% takes 30% of the time

### Protecting Your Sanity

- Establish communication schedule with contractor

- Keep decisions list handy

- Budget for meals out

- Plan an escape (visit family for a weekend)

- Focus on the end result

## Questions for Your Contractor

- What's the realistic construction timeline?

- What could cause delays?

- When do you need final decisions?

- How do you handle discovery issues?

- What's the communication process?

- When will we have a working sink?

Kitchen renovations are disruptive but temporary. Knowing what to expect makes the process manageable.

The Bottom Line

Contact us to discuss your renovation project. We're happy to answer any questions you have.

Ready to Start Your Basement Project?

Get a free, instant estimate for your Ottawa basement renovation. No obligation - just accurate pricing in 60 seconds.

Get Free Estimate